Projects

CSUN Energy Systems

Special Project Achievements

Boeing DOE 100kW CPV POM

Boeing DOE 100kW CPV POM

Construction :
Proof of Manufacturing for
triple junction concentrated
Solar Photovoltaic system.

Jan 2010 - May 2010
DOE grant funded Boeing CPV development project.
100kW of grid connected CPV demonstration project
Project management and installation by CSUN Facility team.

Subtropical Rainforest

Subtropical Rainforest

Construction :
Waste Water Utilization for
Irrigation:
CO2 Utilization:

May 2008 - May 2009

9,000+ Gallons Per Day from Fuel Cell & Chiller Plant
Fuel Cell CO2 Byproduct for Rainforest CO2 Enrichment
(& Optimal Sequestration).

Satellite Chiller Plant

Satellite Chiller Plant

Construction :
Energy Utilization:
Cooling Capacity:
Heat Recovery:
Efficiency:

January 2008 - May 2009
Powered by the Fuel Cell
2,000 Tons
AC Reject Heat Used to Sustain Rainforest.
0.62 to 0.78kW/Ton

1 MW Fuel Cel

1 MW Fuel Cell

Construction :
CO2 Avoidance:
Total Project Electrical
Output:
Heat Recovery:

April 2006 - January 2007
6,400 Tons per MW / year

1 MW
220,000 Therms per Year

B2 Photovoltaic Project

B2 Photovoltaic Project

Construction :
Total Project Cost:
Total Electrical Output:
Annual Electrical Output:
% Total Campus Electrical

March 2003 - February 2005
$3,457,874.64
467 kW
610,000 kWh/year

E6 Photovoltaic Project

E6 Photovoltaic Project

Construction :
Total Project Cost:
Total Electrical Output:
Annual Electrical Output:
% Total Campus Electrical

June 2002 - March 2003
$1,971,318.07
225 Kw
275,000 kWh/year

Micro Turbine Installation

Micro Turbine Installation

Construction :
Total Electrical Output:
Heat Recovery:
% Total Campus Electrical
Consumption:

July 2001 - October 2001
30kW per Micro Turbine 180kW Total
26,000 Therms per Year

3%